Date | Venue | Fee | |
---|---|---|---|
01 Sep - 05 Sep 2025 | Istanbul - Turkey | $ 5,950 | Register Now |
20 Oct - 24 Oct 2025 | Dubai – UAE | $ 4,950 | Register Now |
08 Dec - 12 Dec 2025 | London - UK | $ 5,950 | Register Now |
About the Course
When a project has been fully commissioned and started up, the project will also be a financial success, with the investors receiving their expected returns. When a project has yet to be fully commissioned and started up, it is improbable that it could be a financial success. From an investor's perspective, the project is a disaster.
After completing the commissioning for all the systems (utilities & process) and achieving the ready-for-start-up certificate, it will start discussing the plant start-up until the plant operation and transferring the products from off-spec to on-spec products. It will discuss the plant performance test and how to hand over the plant to the client.
This 5-day interactive Commissioning & Start-Up with API RP 1FSC Foundation training course will empower the delegates with keen insight into chemical processes pre-commissioning/commissioning and start-up for petroleum refining & petrochemical and gas plants as it will concentrate on all the project phases, which include the construction and pre-commissioning activities until achieving the Project Mechanical Completion (MCC) and systems ready for commissioning. Moreover, we will discuss all the commissioning activities procedures for all the utilities and process systems in detail.
Core Objectives
This training course will give insights into the systems completion and familiarity with vital strategies for successful Commissioning and Start-Up of projects, on time and safely, embedded within the guidelines of API Recommended Practice, 1 FSC 1st Edition.
The delegates will achieve the following objectives:
- Achieve successful Commissioning & Start-Up (CSU) on any project
- Justify a budget for Commissioning & Start-Up (CSU)
- Apply the systemisation process and formulate the Start-Up sequence of priority Systems
- Perform Gap Analysis and know how to use the results
- Plan and execute specialist off-site Pre-Commissioning
- Persuade major stakeholders like Construction to be successful in the Commissioning & Start-Up (CSU) process
Training Approach
This training course will utilise various proven adult learning techniques to ensure maximum understanding, comprehension and retention of the information presented; it includes comprehensive challenging and electronic training materials, copies of all presentation material, and relevant computer simulations and videos to help understand the various topics.
The Attendees
This training course is also highly recommended to all involved in the Systems Completion, Pre-commissioning, Commissioning, Startup, and Handover process of new plants.
Likewise, it will be valuable to the professionals but not limited to the following:
- Commissioning Managers
- Commissioning Engineers
- Commissioning Superintendents
- Commissioning Supervisors
- CSU Leads
- Process Engineers
- Maintenance Engineers
- QA/QC Engineers
- Technical Support Engineers
- Safety Engineers
- Field Operators
- Maintenance Technicians
- Safety Officers
Daily Discussion
DAY ONE: OVERVIEW
- Introduction to Commissioning and Start-Up (CSU) Process
- Influence Curves and Planning
- Safety & Environmental Considerations
- Setting a Budget for CSU
- Gap Analysis
- The Project Phases
- The Difference between Pre-commissioning and Commissioning
DAY TWO: PREPARATION I
- The Commissioning Manager & Commissioning & Start-Up (CSU) Team
- CSU Team Roles and Responsibilities
- Risk Assessments
- Systemisation, Completions Pyramid, Start-Up Sequence, and Turnover Process
- Pre-commissioning Activities List per each System
- Commissioning Activities List per each System
- How do you decide the start-up activities based on the system and the process?
DAY THREE: PREPARATION II
- Introduction to Systemisation, Battery Limits on P&IDs: Getting Stakeholder Agreement
- Introduction to System Priority Sequence for Initial Start-Up: Getting Stakeholder Agreement
- Dynamic Commissioning Procedures
- Pre-commissioning and Commissioning Phases Requirements:
- Manpower
- Devises
- Tools and Equipment
- The Priority for the Systems from the Commissioning Team Point of View
- Safety Considerations During CSU
DAY FOUR: IMPLEMENTATION
- Progress Tracking & Reporting
- Factory Acceptance Testing and Preservations
- Tags, Check Sheets, Certificates, and Punch Listing
- Specialist Subcontractors for Cleaning, Drying, Leak Testing and Oil Flushing
- Completions Pyramid and Turnover Process
DAY FIVE: CLOSE-OUT
- Pre-Start-Up Safety Review (PSSR) and Management of Change
- Handover to Operations
- Planning for the First Shutdown
- Critical Success Factors in Commissioning & Start-Up (CSU)
- PAC Punch Items Closure
- Performance Test